KNAUF manufacturing plant

2006  ·  Manufacturing halls and warehousing

Price (excl. VAT) CZK 349,000,000

This was the construction of a manufacturing plant for the production of fibreglass thermal insulation covering a floor area of 21,000 m2. The delivery of the construction part of the buildings including TBE ducts and technological media (with the exception of electrotechnical installations) included: Main manufacturing plants – SO 01, SO 04 – melting of glass and fibre extrusion, SO 02 – technological line, SO 03 – packaging, shipping and logistics, Auxiliary structures – a transformer station and a switch room, a cooling unit machine shop, HPA, administration, material warehouses and other technological structures. The structure was based on steel construction including administration and all technological elements – cooling, HPA, industrial gasses, etc.

  • client
    Knauf Insulation s.r.o.
  • PERIOD OF PERFORMANCE
    08/2005 06/2006
  • LOCATION
    Krupka